Photo of MetroBus construction work near Great Stoke Roundabout.

MetroBus build: May progress report

By Jim Aitken, community liaison officer at Alun Griffiths Ltd. Bradley Stoke Way (BSW) All carriageway surfacing is now complete, including road markings and anti-skid. Landscaping is now taking place along BSW to the verge and swale areas, forming the embankments’ profiles so they may receive turfing and planting – this is very weather dependent. It is our intention to

Continue reading
Photo of MetroBus construction work near Great Stoke Roundabout.

MetroBus construction: April progress report

By Jim Aitken, community liaison officer at Alun Griffiths Ltd. Bradley Stoke Way (BSW) Continuing the finishing works for this area, areas of anti-skid surface at the junction of Orchard Gate, Woodlands Lane and Patchway Brook Roundabout will be undertaken outside of peak hours (after 7pm) during May, due to the limited space available and potential traffic impact. Now the

Continue reading
The Woodlands Lane junction with Bradley Stoke Way, fully reopened after being closed for 559 days for MetroBus roadworks.

MetroBus project: February progress report

By Jim Aitken, community liaison officer at Alun Griffiths Ltd. Bradley Stoke Way On Tuesday 14th February, following just over four weeks of night time surfacing between the Aztec West and Patchway Brook roundabouts, and working jointly with South Gloucestershire Council’s (SGC’s) signalisation team, the traffic lights at the Woodlands Lane and Orchard Gate junctions were commissioned and switched on.

Continue reading
MetroBus construction work gets under way at the southern end of Bradley Stoke Way, on the southbound approach to Great Stoke Roundabout.

MetroBus work at southern end of Bradley Stoke Way to start next week

MetroBus contractors Alun Griffiths have announced that they will commence construction of the final stretch of new bus lane on Bradley Stoke Way next week (w/c Monday 27th February). The work area is located at the southern end of Bradley Stoke Way between Great Meadow Roundabout (junction with Baileys Court Road) and Great Stoke (Rabbit) Roundabout. Vegetation clearance at the site began several

Continue reading
Overnight resurfacing work on Bradley Stoke Way, as part of the MetroBus project.

Five-way traffic lights to be used for final phase of Bradley Stoke Way resurfacing

MetroBus contractors Alun Griffiths have confirmed plans to complete the resurfacing of Bradley Stoke Way over the first two nights of this week, which will involve the use of five-way traffic lights around Patchway Brook Roundabout (near Aldi). It is anticipated that traffic control will be active from 8pm each night. A Griffiths spokesperson said: “Having now concluded the night-time surfacing along

Continue reading
Roadside sign announcing closure of Woodlands Lane for 18 weeks from 2nd September.

Woodlands Lane junction set to be fully reopened by end of February

MetroBus contractor Alun Griffiths and South Gloucestershire Council say they are on schedule to have the junction of Woodlands Lane with Bradley Stoke Way fully reopened by the end of February, subject to weather conditions allowing resurfacing operations to be completed as planned. The Woodlands Lane junction was closed to all traffic on 2nd September 2015, for an estimated 18

Continue reading
Sign advertising planned overnight and weekend closures of Bradley Stoke Way during January 2017. The road closures are associated with construction of the North Fringe to Hengrove Package MetroBus route.

Overnight closures of Bradley Stoke Way (eastbound) for five nights this week

MetroBus contractors Alun Griffiths have confirmed that overnight closures of Bradley Stoke Way for final resurfacing will continue from Monday to Friday this week (6th to 10th February), between the hours of 8pm and 5am. The closures this week will be eastbound-only, covering either the full section between the Aztec West Roundabout and Patchway Brook Roundabout (near Aldi) or the shorter

Continue reading